Contractors told to provide complete safety gear to Orange Line workers

Contractors told to provide complete safety gear to Orange Line workers

LAHORE: Underlining the requirement for offering need to the security of work and authorities of various utility administrations taking a shot at Lahore Orange Line Metro Train Project, guiding board of trustees administrator Khwaja Ahmad Hassaan requested arrangement of wellbeing rigging to the specialists by the temporary workers.

Leading the week after week advance audit meeting here on Wednesday, he looked for a nitty gritty report from the venture chiefs worried in such manner.

“No bargain can be made on human lives for the sake of expedient execution of the work,” he said.

He guided the Safe City Authority authorities to frame distinctive groups of the office and guarantee their nearby coordination with each other. Streets burrowed for laying link for surveillance cameras and different purposes must be repaired at the most punctual to maintain a strategic distance from open bother, he said.

Mr Hassaan requested a constitution of a team containing authorities of the Water and Sanitation Agency (Wasa) and Lahore Waste Management Company (LWMC), to guarantee round-the-clock cleanliness of zones around Haji Camp, Nichleson Road, to encourage travelers.

He educated the meeting regarding the administration’s choice to develop new office working for Shalimar Town in China Scheme, Gujjar Pura, as the old building arranged on the GT Road had been gained for the metro prepare extend.

The meeting was informed that so far 72 for each penny of the common work on Orange Line extend had been finished. Advance on Package-I from Dera Gujjaran to Chauburji was 85.7pc, on Package-II from Choburji to Ali Town it was 53pc, on Depot close Dera Gujran 77pc, while on Stabling Yard close Ali Town it was 73.5pc.

The meeting was informed that dim structure of all the 11 hoisted stations along Package-I and five stations along Package-II of the venture had been given over to NORINCO for electro-mechanical works. The dark structure of another five stations would be given over to the temporary worker before current month’s over, while the staying three stations will be given over by Aug 14.

The meeting was additionally educated that five arrangements of prepare, each containing five autos, had so far been fabricated which would soon be transported to Pakistan. The game plans for stopping these mentors were being finished at the station at Dera Gujjran by laying a two kilometers track.