The LESCO administration has issued a statement stating that the demand notice charge for a three-phase meter has increased from Rs33,500 to Rs63,450.
The notification states that the increased costs will be implemented starting from July 1.
Procedure for applying for a new connection with LESCO
- To initiate the application procedure, please access the provided link (http://www.enc.com.pk/).
- When submitting a form, you must provide the following information:
Select one connection type from the following options: Domestic, Commercial, Industrial, Agriculture, Tubewell, Temporary, General Services, Residential Colonies, Street Light.
- Additionally, you will need to provide property information for the location where you intend to build the new energy connection.
- Once you have completed and uploaded all the necessary information and documents, proceed to submit the application form.
- Require a hard copy of the application form you have submitted.
Please ensure that all stated documents are attached to this application.
Further information: LESCO officials have ceased their strike following the guarantee from the FIA that there will be no raids related to overbilling.
- Forward or deliver this entire file (comprising of the application form and necessary papers) to the appropriate office.
- The LESCO demand notice will be issued once the provided documents and information have been verified.
- The next step is to make payment for the LESCO demand notice at the designated bank.
- Once the demand notice has been paid, a copy should be provided to the relevant authority for further processing.
- In this final stage, the relevant office will verify the payment made in response to the demand notice. Once the verification is complete, they will proceed to install the connection.